PMI PMI-PgMP Free Practice Questions — Page 3

Program Management Professional • 5 questions • Answers & explanations included

Question 11

You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

A. Quality control
B. Quality control
C. Direct and manage program execution
D. Quality assurance
Show Answer & Explanation

Correct Answer: B. Quality control

Benefits management is the program management process specifically focused on defining, creating, maximizing, delivering, and transitioning program benefits to operations — it is the core differentiator between program management and project management. Option A (quality control) involves inspecting work results for defects and ensuring deliverables meet standards, which is unrelated to benefits delivery and transition. Option C (direct and manage program execution) is about performing the work defined in the program management plan, not specifically about delivering and transitioning benefits to operations. Option D (quality assurance) focuses on auditing processes to ensure quality standards are being applied, which has no direct relationship to benefits delivery or transition to operations.

Question 12

What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of return is five percent?

A. $1,550,850
B. $3,532,000
C. $2,502,750
D. $2,661,750
Show Answer & Explanation

Correct Answer: D. $2,661,750

The Present Value (PV) formula is: PV = FV / (1 + r)^n where FV = $3,567,000, r = 0.05, and n = 6. Calculating: (1.05)^6 = 1.3401 → PV = $3,567,000 / 1.3401 = $2,661,750 Option A ($1,550,850) is incorrect — it represents an overly aggressive discount that does not match the 5% rate over 6 years. Option B ($3,532,000) is barely below the future value, suggesting almost no discounting, which is mathematically wrong for 6 years at 5%. Option C ($2,502,750) applies too large a discount factor, possibly using an incorrect rate or period in the calculation.

Question 13

You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

A. Communicate why the change request was rejected and record the results in the lessons learned documentation for your program.
B. Inform the stakeholders that their change requests have been rejected.
C. Communicate the change request status to the stakeholders and record the results of the change request in the change register.
D. Inform the stakeholders why their change requests have been rejected.
Show Answer & Explanation

Correct Answer: C. Communicate the change request status to the stakeholders and record the results of the change request in the change register.

In program management, all change requests — approved or rejected — must be documented in the change register and their status communicated to relevant stakeholders. This ensures full traceability, transparency, and audit trail regardless of the decision outcome. Option A (lessons learned documentation) is not the primary repository for change request outcomes — the change register is, and lessons learned serve a different, broader purpose at program closure. Option B (inform stakeholders of rejection) is partially correct but incomplete — it omits the critical step of recording the decision in the change register. Option D (inform stakeholders why rejected) is also partially correct but again incomplete — communication alone without formal documentation in the change register does not satisfy program management governance requirements.

Question 14

Where are negative risks recorded?

A. Negative risk register
B. Risk management plan
C. Risk register
D. Issues log
Show Answer & Explanation

Correct Answer: C. Risk register

The risk register is the single repository where all risks — both positive (opportunities) and negative (threats) — are identified, analyzed, and tracked throughout the program or project lifecycle. Option A (negative risk register) does not exist as a PMI artifact — there is no separate register for negative risks. Option B (risk management plan) defines the approach, methodology, and processes for managing risks but does not record individual risks — it is a planning document, not a tracking document. Option D (issues log) records issues that have already occurred — problems that are current and need resolution — while risks are potential future events that have not yet happened.

Question 15

You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

A. $400,498
B. $521,345
C. $505,620
D. $385,450
Show Answer & Explanation

Correct Answer: A. $400,498

Using the Present Value formula: PV = FV / (1 + r)^n where FV = $450,000, r = 0.06, and n = 2. Calculating: (1.06)^2 = 1.1236 → PV = $450,000 / 1.1236 = $400,498 Option B ($521,345) is higher than the future value, which is mathematically impossible for a present value calculation — PV must always be less than FV when discounting. Option C ($505,620) is also greater than the future value, making it equally impossible as a present value result. Option D ($385,450) applies too large a discount factor, suggesting a higher rate or longer period was incorrectly used in the calculation.

Ready for the Full PMI-PgMP Experience?

Access all 113 pages of practice questions and simulate the real exam with timed mode.

Start Interactive Quiz →