A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?
Show Answer & Explanation
Correct Answer: A. Consult the risk register for an appropriate planned risk response and implement.
The project manager proactively identified this exact risk during planning — that a critical technical resource might not be available. Since the risk was already identified and documented in the risk register, the first action should be to consult the risk register and implement the pre-planned response. This is the core purpose of risk management: plan ahead so you can act quickly when risks materialize. Option B (rescheduling) might be a valid response, but only if it's part of the planned risk response — you don't skip the register. Option C (excluding the task) is inappropriate because the task is on the critical path and tied to business requirements. Option D (updating lessons learned) is something you do after responding to the risk, not as the first action. The PMI approach emphasizes using planned risk responses before improvising.