PMI PMP Free Practice Questions — Page 1

Project Management Professional • 5 questions • Answers & explanations included

Question 1

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?

A. Consult the risk register for an appropriate planned risk response and implement.
B. Revise the project management plan and move the task to a time when the technical resource will be available.
C. Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
D. Update the lessons learned report and the risk log to reflect that this risk has materialized.
Show Answer & Explanation

Correct Answer: A. Consult the risk register for an appropriate planned risk response and implement.

The project manager proactively identified this exact risk during planning — that a critical technical resource might not be available. Since the risk was already identified and documented in the risk register, the first action should be to consult the risk register and implement the pre-planned response. This is the core purpose of risk management: plan ahead so you can act quickly when risks materialize. Option B (rescheduling) might be a valid response, but only if it's part of the planned risk response — you don't skip the register. Option C (excluding the task) is inappropriate because the task is on the critical path and tied to business requirements. Option D (updating lessons learned) is something you do after responding to the risk, not as the first action. The PMI approach emphasizes using planned risk responses before improvising.

Question 2

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality. What should the project leader have done to ensure success?

A. Asked the team to create an impediment log and keep it updated for use in the next sprint planning
B. Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery
C. Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints
D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments
Show Answer & Explanation

Correct Answer: D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

In agile, the project leader (Scrum Master) should act as a servant leader who empowers the team to self-organize and improve. The key issue here is that fast-tracking was imposed on the team, leading to low quality or fewer features — a directive approach that failed. Option D aligns with the agile principle of empowering teams to find their own ways to improve processes and remove impediments. Option A (impediment log) is a tool but doesn't solve the root cause. Option B (directing solutions) is too prescriptive and contradicts servant leadership. Option C (adding impediments to the backlog) is incorrect because impediments are not product backlog items — they are blockers to be resolved immediately. Agile retrospectives and continuous improvement are the correct mechanisms here.

Question 3

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team. What should the project manager do?

A. Include the customer in daily project activities to gain the required guidance
B. Plan ahead and define the best way to review the deliverables with the customer
C. Request the customer to clarify all requirements at the start of each iteration
D. Ask the customer to review the deliverables in each iteration based on their availability
Show Answer & Explanation

Correct Answer: B. Plan ahead and define the best way to review the deliverables with the customer

The root problem is that the customer is frequently unavailable for reviews, causing delays and rework. The project manager should proactively plan ahead and define the best way to engage the customer for reviews. This means establishing a clear, agreed-upon review process (schedule, format, communication channel) that works for the customer. Option A (including customer in daily activities) is excessive and unrealistic. Option C (clarifying all requirements upfront) goes against iterative/agile principles. Option D (review based on availability) is essentially the current situation and doesn't solve the problem. Planning the engagement approach ensures predictable feedback loops and reduces rework.

Question 4

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date. What should the project manager do?

A. Meet with the design team manager to inform them of the current status and request an additional designer
B. Ask the software engineer to move forward without completing the important feature
C. Contact the design team manager and ask to reconsider the priority list based on the latest situation
D. Meet with the designer to share the current status and develop a solution to complete the task
Show Answer & Explanation

Correct Answer: D. Meet with the designer to share the current status and develop a solution to complete the task

The blocker is a specific task that the designer needs to complete. The most effective first step is to meet directly with the designer to understand the situation and collaboratively develop a solution. This is servant leadership — removing impediments by working with the people involved. Option A (requesting additional designer) escalates prematurely without first understanding the root cause. Option B (skipping the feature) is unacceptable because the feature is important for regulatory compliance. Option C (reprioritizing the design team's work) may be needed but goes over the designer's head without first trying direct collaboration. Always try to resolve blockers at the lowest level first before escalating.

Question 5

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?

A. A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions
B. A hybrid approach will allow the project manager to revise the product specifications
C. A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction
D. A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties
Show Answer & Explanation

Correct Answer: C. A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction

The hybrid approach was chosen because there are two competing constraints: unclear requirements (favoring agile/adaptive) and a fixed regulatory delivery date (favoring predictive/waterfall). A hybrid approach combines both — using adaptive methods to handle evolving requirements while using predictive planning to manage the fixed deadline. Option A focuses only on starting quickly, missing the date constraint aspect. Option B is vague and doesn't address the core reasons. Option D is incorrect because no approach can "eliminate" uncertainties — it can only manage them. The hybrid approach is specifically designed for situations where neither pure agile nor pure predictive fully fits the project context.

Ready for the Full PMP Experience?

Access all 278 pages of practice questions and simulate the real exam with timed mode.

Start Interactive Quiz →