PMI CAPM Free Practice Questions — Page 2

Certified Associate in Project Management • 5 questions • Answers & explanations included

Question 6

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

A. create the project management plan.
B. identify the project objectives.
C. review and update stakeholder engagement.
D. create the schedule baseline.
Show Answer & Explanation

Correct Answer: C. review and update stakeholder engagement.

Phase transitions are key checkpoints where the project manager should review and update stakeholder engagement, as stakeholder needs and influence levels can change as the project moves forward. The PMBOK® Guide emphasizes that stakeholder engagement is a continuous process revisited throughout the project lifecycle, especially at phase gates. Option A is incorrect because the project management plan is created during the planning phase, not at phase transitions. Option B is incorrect as project objectives are identified during initiation, not mid-project. Option D is incorrect because the schedule baseline is established during planning and is not recreated at phase transitions.

Question 7

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A. 8
B. 18
C. 36
D. 40
Show Answer & Explanation

Correct Answer: C. 36

The formula for communication channels is n(n-1)/2, where n = total number of people. The total participants are: 1 project manager + 4 stakeholders + 4 team members = 9 people. Applying the formula: 9(9-1)/2 = 9×8/2 = 36 channels. Option A (8) is incorrect as it ignores most participants. Option B (18) would result from miscounting participants or misapplying the formula. Option D (40) is incorrect and does not result from any correct application of the formula. This is a frequently tested CAPM formula that candidates must memorize.

Question 8

A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?

A. Review stakeholder register and meeting
B. Data analysis and communication skills
C. Data gathering and data analysis
D. Communication skills and cultural awareness
Show Answer & Explanation

Correct Answer: D. Communication skills and cultural awareness

In the context of project management and the PMBOK guide, capturing stakeholder interest—especially during initial meetings—relies heavily on the project manager's "Interpersonal and Team Skills." Communication skills, such as active listening and feedback, are essential for ensuring that stakeholder concerns are heard and their interests are documented accurately. Cultural awareness is equally critical as it allows the project manager to tailor their approach to the specific backgrounds and expectations of each stakeholder, which fosters trust and minimizes misunderstandings.

Question 9

Select three processes that are associated with Project Schedule Management? (Choose three.)

A. Define Activities
B. Plan Resource Management
C. Estimate Activity Durations
D. Develop Schedule
E. Acquire Resources
Show Answer & Explanation

Correct Answers: A. Define Activities; C. Estimate Activity Durations; D. Develop Schedule

These three are core processes within Project Schedule Management. Option B (Plan Resource Management) belongs to Resource Management, and Option E (Acquire Resources) also belongs to Resource Management, not Schedule Management.

Question 10

What are the project management processes associated with project quality management?

A. Plan Quality Management, Manage Quality, and Control Quality
B. Plan Quality Management, Manage Quality, and Cost of Quality
C. Manage Quality, Customer Satisfaction, and Control Quality
D. Customer Satisfaction, Control Quality, and Continuous Improvement
Show Answer & Explanation

Correct Answer: A. Plan Quality Management, Manage Quality, and Control Quality

These are the three official PMBOK® processes in Project Quality Management. Options B, C, and D incorrectly include "Cost of Quality," "Customer Satisfaction," and "Continuous Improvement," which are concepts/tools, not process names.

Ready for the Full CAPM Experience?

Access all 97 pages of practice questions and simulate the real exam with timed mode.

Start Interactive Quiz →